SNTGN TRANSGAZ SA MEDIAS notifies all persons concerned that a “Joint Development Agreement” on the interconnection of the high-pressure Hungarian Gas Transmission System with the Romanian Gas Transmission System – by building of a pipeline in the direction Szeged-Arad – was concluded with the Hungarian Company - FGSZ NATURAL GAS TRANSMISSION CLOSED COMPANY LIMITED BY SHARES, on July 1st, 2008. On the Romanian territory, the DN700/PN63 pipeline is of approx. 62 km between the Horia (close to Arad) connection point and the Csanadpalota (Nadlac) Romanian – Hungarian cross-border point. Out of the total 62 km of pipeline, 36.7 km, between Horia and Pecica, have already been built. 
  The maximum transmission capacity of the interconnection pipeline is of 4.4 bcm/year associated to an average hourly flow rate of 500 thousand cm/hour.