BULGARIA - ROMANIA INTERCONNECTION,
between Giurgiu (Romania) and Russe (Bulgaria)


Transgaz EEPR Bulgartransgaz

 

Project Purpose:

The main purpose of the project is to increase the security of gas supplies to Romania and Bulgaria.

The objectives considered are:

            - Diversification of natural gas supply for Romania and Bulgaria;
            - Ensuring continuity and security of gas supplies to residential and industrial consumers in crisis situations and gas supply shortages;
            - Ensuring conditions for bi-directional flow of natural gas;
            - Increasing integration of regional natural gas market in south-eastern Europe;
            - Increasing the level of interconnectivity

Project description:

Specifications:

            - Maximum transmission capacity - 1.5 billion cubic meters per year;
            - Minimum transmission capacity - 0.5 billion cubic meters per year;
            - Maximum pressure - 40 bar
            - Minimum pressure - 29 bar;
            - Pipe diameter - DN 500 mm.

Implementation of the project involves the completion of the following works:

            - Construction of two Gas Metering Stations, G.M.S. Giurgiu and G.M.S. Russe;
            - Construction of a DN 500 mm, PN 40 bar pipeline, with a length of about 5.2 km between G.M.S. Giurgiu and the undercrossing point located on the Romanian bank of the Danube;
            - Construction of a DN 500 mm, PN 40 bar pipeline, with a length of about 15.4 km between G.M.S. Russe and the undercrossing point located on the Bulgarian bank of the Danube;
            - Construction of two DN 500 mm, PN 40 bar pipeline sections undercrossing the Danube river (main pipe and the backup pipe) with a total length of 4.14 km (2.07 km x 2 sections).

            Total estimated project value (eligible values for E.U. co-financing) is about 24 mil. Euro, broken down as follows:
            - TRANSGAZ S.A. - about 10 mil. Euro
            - BULGARTRANSGAZ E.A.D. - about 14 mil. Euro

TRANSGAZ and BULGARTRANSGAZ will jointly implement the project observing the decision for E.U. funding Nr. C (2010) 5962 of 06/09/2010, in accordance to the E.E.P.R. programme (European Energy Programme for Recovery) provisions. Under this programme a E.U. co-financing in the amount of about 8.9 mil. Euro has been allocated for this project, splitted between the project partners as follows:
- TRANSGAZ  S.A. - about 4.6 mil. Euro;
- BULGARTRANSGAZ   E.A.D. - about 4.3 mil. Euro.

The amount co-financed by the European Commission represents 37.48% of the estimated total value of the project.

"The sole responsibility of this publication lies with the author. The European Union is not responsible for any use that may be made of the information contained therein."

 

 